Journal Archive page for May 2008
Excavation work
-
Peter Wilson
Project Director - 28 May 2008
Excavation work – which will include a new 7 metre deep sub-stage basement – has begun with the excavation for the west core of the new theatre.
The completion of the piling works
-
Peter Wilson
Project Director - 21 May 2008
Last week saw the achievement of a major project milestone: the completion of the piling works by Cementation.
First tower crane arrives
-
Peter Wilson
Project Director - 7 May 2008
The most significant activity on site this week is the erection of the first tower crane in the old Royal Shakespeare Theatre car park.