Journal Archive - February 2008
Piling contractor moves on site
-
Peter Wilson
Project Director - 27 February 2008
Preparations for the piling contractor to begin work were completed. This week sees the beginning of a new phase with the arrival of the piling contractor, Cementation, and their equipment.
Flood compensation works completed
-
Peter Wilson
Project Director - 20 February 2008
The flood compensation works in The Dell were also completed. The area has been sown with a mixture of grass and wildflower seeds and will remain fenced off whilst the new seeds germinate and establish themselves.
Fly tower roof demolished
-
Peter Wilson
Project Director - 13 February 2008
Preparations are under way for the demolition of the fly tower roof (not visible from the street as it is below the fly tower parapet) and for the demolition of the stage door and of the block between the Swan auditorium and the Swan Library building to the south of the stage wing.
Temporary supports installed
-
Peter Wilson
Project Director - 6 February 2008
The last elements of demolition adjacent to the Fountain Staircase and balcony stair continue and preparations for the piling contract are nearing completion. The installation of temporary supports within the fly tower basement have begun.