Tower lift shaft
-
Peter Wilson
Project Director - 15 October 2008
Work on site continues apace with the majority of the flytower steelwork now in place and a similarly large quantity of steel erected on the riverside to form the new dressing room block.
For those of you peeking over the hoardings this week you can now see the first level of the tower lift shaft. This will be constructed level by level over the next few weeks then the exterior of the tower will be constructed around it.