Backstage accommodation steelwork
-
Peter Wilson
Project Director - 01 October 2008
Last week ended with the installation of the roof trusses of the auditorium using a very large mobile crane. They are the creamy yellow steelwork adjacent to the existing flytower and they weigh in excess of 30 tonnes each, being capable of supporting all of the equipment and scenery for the thrust stage.
This week's activity is a combination of completion of the concrete works and the continued installation of the lesser steelwork for the backstage accommodation.